Parbati Hydroelectric Project (HEP) Stage-II

Run-of-the-river scheme to harness hydro potential of the lower reaches of the river Parbati.
Technical Assistance & supply of specialized personnel

Excavation of a portion of the Headrace Tunnel of about 4349 m length (RD 15340 m to RD 10991 m) of 6.0 m finished diameter circular shaped to be excavated by TBM.

1

Manikaran quartzite and Bandal granite/Gneissose granite with rock covers ranging from 850 to 1300 m.