Shaanxi Yinhongjishi Water Diversion Project, Lot IV

TBM modification and excavation of remaining tunnel stretch

Project details:

  • Design of TBM modifications from DS to DSU.
  • Excavation and lining of the chamber for the TBM modification and re-starting operations.
  • Excavation and lining of the remaining tunnel stretch.
  • Excavation and lining of the tunnel widening for the TBM final disassembling.
  • Topographic surveys.
  • Supply of technical and administrative personnel.
  • Supply of materials.

 

Previous Next

Geology summary: marble interspersed with levels of chloritic and carbon schists; chloritic schists with Quartzite