Shatin to Central Link ‐ Contract 1107 (Diamond Hill to Kai Tak Tunnels)

Supply of TBM (EPB.0740.148) and back-up

Tunnelling works from the new Kai Tak Station to the upgraded Diamond Hill Station, as part of the new Shatin to Central Link for MTRC. The 850 m twin tunnel alignment, with cross passages, is located in the area previously occupied by the old Kai Tak International Airport, and has been constructed using a 7.4 m diameter EPB (Earth Pressure Balance) TBM, using SFRC segments forming the concrete lining that provides better long term durability.

Check the breakthrough video.

Anterior Siguiente

Granite and weatered granite with silt and gravel interbedded deposit